The Government delegate and the president of the CHS visit the completion of the works
The Government delegate, Rafael González Tovar, president of the Hydrographic Confederation of Segura (CHS), José Salvador Fuentes Zorita, and the mayor of Moratalla, Juan Llorente, today visited the works to the channelization of the Rambla de la Talanquera in the town of Moratalla, conducted by the Public Works and Services Company, SA, which has invested 311,223 euros.
This project, part of the Special State Fund for Promoting the Economy and Employment (on whose execution has been entrusted to the CHS), solve the problems caused by the overflowing and flooding the avenue of Talanquera in final section, where rainwater collects all of the urban area of Moratalla, coinciding with a significant reduction of the channel, which effectively disappears causing the resulting damage.
The project has seen the demolition of several elements that prevent the proper drainage, after which, we proceeded to dig the trench and the construction of the basis on which to settle the precast concrete frames are the first tranche channeling.
After placement of precast concrete frames are running the same filling and forming the platform on which to build a park and recreation facilities for use and enjoyment of moratalleros.
This new green space has a floor of beaten earth or albero, which are located on different areas with benches and street furniture and playground.
In addition to these actions, we have implemented an access from the street D.
Thomas the Cure.
Also access from the San Antonio Crossing is via a gravel path, the path runs along the same path that the underground concrete frames.
The second section of the drive consists of two parallel reinforced concrete pipes of 1,200 mm in diameter, obliquely crossing of the crossing of San Antonio to reach the mouth on the opposite side of the street.
Finally has recovered asphalt layer crossing the street in San Antonio.
The transition between the indictment made with frames and driving consists of reinforced concrete pipe has been spared with the construction of a large pit, located at the intersection of the avenue to the crossing of San Antonio.
The last of the actions of the implementation of the mouth of the pipeline, which lies in the natural drainage area of the promenade, opposite the San Antonio Crossing, next to the garden plots.
Source: CHS